M/s Saisudhir Energy Ltd. (Appellant) vs. M/s NTPC Vidyut Vyapar Nigam Ltd (2026)

Supreme Court Upholds Liquidated Damages in Delayed Solar Project, Limits Appellate Interference in Arbitration.
Supreme Court of India

Legal provisions involved: Sections 34 & 37 of the Arbitration and Conciliation Act, 1996; Section 74 of the Indian Contract Act, 1872.

Judgement by: Supreme Court of India

Judge/Bench: Justice P.S. Narasimha and Justice Atul S. Chandurkar

Facts

Saisudhir Energy Ltd. signed an agreement with NVVNL to set up a 20 MW solar power plant under a government solar mission. The plant was not completed on time. Because of the delay, NVVNL imposed liquidated damages as mentioned in the contract. An arbitral tribunal gave a mixed decision. Later, a Single Judge increased the compensation to 50% of the contractually fixed damages. The Division Bench reduced this amount. Both sides then appealed to the Supreme Court.

Key legal provisions

Sections 34 & 37 of the Arbitration and Conciliation Act, 1996

Section 74 of the Indian Contract Act, 1872.

Issues raised

Whether actual loss had to be proved?

Whether the court could modify the award; and whether the appellate court could recalculate damages?

Arguments of the case

The company said damages were unfair without proof of loss. NVVNL argued delay in a public project itself caused loss and the damages were pre-agreed.

Judgement

The Supreme Court restored the Single Judge’s order, saying delay in public utility projects itself implies loss and higher courts cannot rework the compensation like an appeal on facts.

Click here to VIEW the full judgement.